As a property developer, our goal is to make the best possible use of the land to achieve the highest combined sales price upon completion, which results in the highest possible profit for our investors as well as ourselves.
In order to formulate a development plan, we need to obtain a land survey which will provide us with essential information such as the exact boundaries of the site and elevation changes which will need to be considered when creating a design.
Determining the best use of the land is a balancing act between several factors: the number of total properties, the quality of each property, and local Council requirements. Generally speaking, as a developer you want to try and fit as many properties onto the site as possible. 600,000 dollars multiplied by six is a bigger number than 600,000 multiplied by five, so more properties is the easiest way to increase the profitability of the property development. That said, development design is more complicated than just tetris-ing as many properties onto the site as possible. You must also ensure that each property is desirable and suitable for market—if it can’t be sold, it’s worth nothing. Zero dollars multiplied by six is still zero.
There are also Council requirements which must be complied with in order to obtain mandatory permits and approvals. To ensure that developers and landowners are building quality homes in their area, and that surrounding homes aren’t being adversely affected, Councils will only grant permits to developments that meet their criteria.
To achieve the most efficient and profitable use of the land, we seek out an architect, and depending on the scale of the development site, a town planner, to assist us with the development design. We believe that engaging with specialists who have experience with the type of development we are undertaking as well as the region we are developing in is a must. Their expertise allows us to quickly create an optimised site plan that will comply with Council requirements and save us time and money later in the project.
Once we’ve selected an architect and town planner, we’ll work with them to create several drafts until we reach a design that we’re happy with. The more specialised design drawings will require consultants to work on them: Geotechnical Engineers, Civil Engineers, Water Supply, Electricity Supply, to name a few. All necessary documents need to be distributed to these consultants so they can begin their work.
We believe that engaging with specialists who have relevant experience is a must.
Once each consultant has completed their work, it needs to be checked for errors, and then cross-checked against the work of all the other consultants to ensure that everything matches and lines up.
All of these design documents are then collated into a Design Package which is submitted to Council.
Submitting a planning application to Council involves a cost, which varies depending upon the type of development, the scale of the development, and the legislation of the location in which you are developing, but it will most likely be a few thousand dollars.
After submitting to Council and paying the required fee you’ll almost always receive a Request for Further Information (RFI). Prior to COVID, it was typically a four to six week wait to hear back from Council after the initial submission. After COVID, with Council’s having large backlogs, it can take even longer. Unfortunately, there’s not much that a developer can do other than wait and politely ask for them to go faster.
The RFI will draw attention to elements of the submission that the Council needs additional information about in order to make their decision. Once the RFI has been received, we have a set period to resubmit plans that address the Council’s requests or the application will lapse and we must resubmit from the beginning and pay the fees again. This period is outlined in the Council’s RFI letter, and is approximately six weeks.
The RFI will draw attention to elements of the submission that the Council needs additional information about in order to make their decision.
As an example, the Council’s RFI may call for additional information related to the height of fences. So in this example, in our response to the RFI we would ensure that we include plans that specify the height of the fences and include a comment explaining that the height of the fences will not impede onto adjoining properties or affect views.
The Council may issue multiple RFIs until they are satisfied they have all the information they need to make a decision, so it’s worthwhile to be thorough upfront in order to minimise delays throughout this process, since each RFI will add two to three months to the duration of the Council application process.
Depending on the nature of the submission, the Council may decide that an Advertising period is required before they approve the submission. In this context, ‘Advertising’ refers to notifying neighbours and locals about the development by placing signs on site. The purpose of Advertising is to provide locals the opportunity to voice their concerns about the development if they are going to be affected by it.
If any appropriate complaints are raised, the submitted plans may be rejected until those objections are addressed. The period of advertising varies per state but is usually around two to four weeks. Once any concerns from neighbours are addressed, we can make a final submission and receive the Council’s decision.
At this point, the Council can either accept the application and grant planning permits, or they can reject it. If the submission is accepted, we can move on to the next step. If the submission is rejected, we can appeal the Council’s decision by taking the case to a civil tribunal.
Having to go to a civil tribunal may add 6-12 months to the total duration of the project so it is far from the ideal situation, but it’s better than abandoning a development. If the appeal is successful, the Council will be required to grant planning permits.